In 2019 we started this $1 million dollar project with J.F Shea Construction to rehabilitate the steel pipe at the Metropolitan Water Districts five pumping plants located in San Bernardino and Riverside Counties in Southern California. This work consists of relining over 2,000 feet of 6-foot diameter discharge piping. This shutdown work is being performed in tow phases, one of which was done in February 2020 and the second shutdown to be done in February 2021. Due to the time constraints of a shutdown of this size at the peak of the work during the 3-week shutdown, we had 25 welders onsite to ensure project coverage and completion.
ClientJ.F Shea ConstructionYear2019Share